On-site technical consultation at Indian Oil Corporation Guwahati Refinery, Assam Indian Oil Corporation Limited, Guwahati Refinery, INDIA January 2025 Completed None
Power System Study for Dumad Plant of Indian Oil Corporation Limited Indian Oil Corporation Limited, Gujarat Refinery, INDIA December 2024 Ongoing ETAP
Power System Study for India Oil Corporation, Haldia Refinery. SNS Technocorp Pvt. Ltd., New Delhi September 2024 Ongoing ETAP
Consulting services for electriccal power system study at Guru Gobind Singh Refinery of HMEL, Bhatinda HPCL-Mittal Energy Limited, Bathinda, Punjab, INDIA July 2024 Completed ETAP
Protection Setting Study for CCP4 230kV GIS of Sembcogen at Banyan, Singapore GE Grid Solutions Pte Ltd (GE Vernova), Singapore June 2024 Completed None
On-site technical consultation at Indian Oil Corporation Guwahati Refinery, Assam Indian Oil Corporation Limited, Guwahati Refinery, INDIA April 2024 Completed None
Relay coordination study for the electrical system at Paste PVC Plant of Chemplast, Cuddalore Chemaplast Sanmar Pvt. Ltd., Cuddalore, Tamil Nadu, INDIA April 2024 Completed ETAP
On-site technical consultation at Indian Oil Corporation Guwahati Refinery, Assam Indian Oil Corporation Limited, Guwahati Refinery, INDIA October 2023 Completed None
Expert Consulting Service for developing Algorithm and Matlab code for enhancement of the Automatic Fault Analysis software (AFA2.0) and development of Web based COMTRADE reader for TNB Malaysia. Comfort Alliance Sdn Bhd., Kuala Lumpur, Malaysia August 2023 Completed Matlab, Python, Django, Javascript & React
Power system and protection studies for MRPL refinery and Aromatic Complex Mangalore Refineries and Petrochemicals Limited, Mangalore, Karnataka January 2023 Completed ETAP
Power system and protection study for CPP electrical system of Guru Gobind Singh Refinery of HMEL HPCL-Mittal Energy Limited, Bathinda, Punjab, INDIA December 2022 Completed ETAP
Power system and protection study for operating refinery electrical power system at IOCL Barauni refinery in parallel with 220kV grid Indian Oil Corporation Limited, Barauni Refinery, Bihar, INDIA December 2022 Ongoing ETAP
Expert Consulting Service for developing Algorithm and Matlab code for selected modules of the Automatic Fault Analysis software of TNB Malaysia. Comfort Alliance Sdn Bhd., Kuala Lumpur, Malaysia September 2022 Completed Matlab
Power system study for grid parallel operation feasibility for Indian Oil Corporation Bongaigaon Refinery Indian Oil Corporation Limited, Bongaigaon Refinery, INDIA June 2022 Completed ETAP
On-site technical consultation at Indian Oil Corporation Guwahati Refinery, Assam Indian Oil Corporation Limited, Guwahati Refinery, INDIA June 2022 Completed None
Feasibility study for new induction motor and DG addition to the LAB electrical system of Tamil Nadu Petroproducts Limited, Chennai Tamil Nadu Petroproducts Limited, Tamil Nadu, INDIA May 2022 Completed ETAP
Overcurrent & Earth fault setting review for BS-VI HT system at Mangalore Refineries and Petrochemicals Limited Mangalore Refineries and Petrochemicals Limited, Mangalore, Karnataka March 2022 Completed ETAP
Generator Protection Setting Calculation for Black Point Power Station, Hong Kong GE Grid Solutions Pte Ltd, Singapore March 2022 Completed None
Protection Setting Study for 400/220kV Mariakani Substation, Kenya GE Grid Solutions Pte Ltd, Singapore March 2022 Completed None
Power System Study for Indian Oil Coporation, Guwahati Refinery for Grid parallel operation Siemens Ltd, Kolkatta January 2022 Completed ETAP
Power System Study for India Oil Corporation, Panipat Refinery & Naptha Cracker Plant SNS Technocorp Pvt. Ltd., New Delhi January 2022 Ongoing ETAP
Algorithm development for Power Quality Module of AFA for TNB Malaysia Comfort Alliance Sdn Bhd., Kuala Lumpur,Malaysia January 2022 Completed Matlab
Power System Study for the plant of TCI Sanmar Chemicals, Port Said, Egypt TCI Sanmar Chemicals S.A.E, Egypt March 2021 Completed ETAP
Protection study for the electrical system of Tamil Nadu Pertroproducts Limited, Chennai Tamil Nadu Petroproducts Limited, Tamil Nadu, INDIA January 2021 Completed ETAP
Protection study for 220/132kV PAC ON substation of CEM Macau GE Grid Solutions Limited, Hong Kong January 2021 Completed None
Online consultancy to troubleshoot the reason for residual current observed in the generator incomers at OMPL, Mangalore and suggest solution to solve problem ONGC Mangalore Petrochemicals Limited, Mangalore December 2020 Completed None
Reactive Power Compensation study for power factor correction at the 6.6kV HDT and SDU S/S of IOCL Haldia Refinery Indian Oil Corporation Limited, Digboi Refinery, INDIA October 2020 Completed ETAP
Algorithm Development for Automatic Fault Analysis System for TNB Malaysia Total Power Solutions, Sdn. Bad, Kuala Lumpur, Malaysia June 2020 Completed Matlab
Protection Setting Study for REALISATION DE LA STN DE DESSALEMENT D’EAU DE MER DE ZARAT Project (De-salination plant) in Tunisia VA TECH WABAG, India March 2020 Ongoing ETAP
Protection setting review for the Captive Power Plant of India Cement at Sankarnagar, Tamil Nadu, INDIA India Cement Limited March 2020 Completed ETAP
Protection Setting Review for 33/11kV NDOOD JHAM Substation of Abu Dhabi Transmission Company ABB, Dubai, UAE March 2020 Completed None
Power system study for IOCL Haldia refinery Power system study of IOCL Haldia refinery February 2020 Completed ETAP
Protection study for the 275, 33 & 11kV TATAU substation of Sarawak Energy Berhad, Malaysia GE Power Services (Malaysia) Sdn Bhd February 2020 Completed None
Onsite consultancy for analysing tripping incident at IOCL Digboi Refinery Indian Oil Corporation Limited, Digboi Refinery, INDIA July 2019 Completed None
Protection study for Al Dhafrah 400kV Switching Station of Abu Dhabi Transmission Compay ABB, Dubai, UAE June 2019 Completed None
Onsite consultancy for reliability improvement at Mangalore Refineries, Karnataka Mangalore Refinery, Karnataka, INDIA April & Dec 2019 Completed None
Protection setting review for the LT system of India Cement at Sankarnagar, Tamil Nadu, INDIA India Cement Limited January, 2019 Completed None
Protection relay setting review for Haldia Refinery of Indian Oil Corporation Limited, West Bengal, INDIA M/s Jeevandeep Enterprise November 2018 Completed ETAP
Protection study for the 275, 132 & 33kV SERUDIT substation of Sarawak Energy Berhad, Malaysia GE Power Services (Malaysia) Sdn Bhd September 2018 Completed None
Onsite consultancy for reliability improvement at Mangalore Refineries, Karnataka Mangalore Refinery, Karnataka, INDIA April & May 2018 Completed None
Power system and protection study for Gujarat Refinery of Indian Oil Corporation Limited, Vadodara, INDIA Siemens Ltd., INDIA March 2018 Completed ETAP
Protection setting review for the Cement plant of India Cement at Sankarnagar, Tamil Nadu, INDIA India Cement Limited January, 2018 Completed None
Protection setting review for Digboi Refinery, of Indian Oil Corporation, INDIA Indian Oil Corporation Limited, Digboi Refinery, INDIA January, 2018 Completed ETAP
Onsite consultancy for reliability improvement at Digboi Refinery, of Indian Oil Corporation, INDIA Indian Oil Corporation Limited, Digboi Refinery, INDIA December, 2017 Completed None
Power system study of IOCL Bongaigaon refinery for INDMAX project L&T, Hydrocarbon Engineering Ltd October, 2017 Completed ETAP
Protection study for Bismayah 400/132/11kV substation, IRAQ ABB Germany September, 2017 Completed None
Harmonic study for analyze the effect of installing capacitor bank at Chennai Petroleum Corporation Limited, INDIA Adarsha Control & Automation, Chennai, INDIA May, 2017 Completed ETAP
Onsite consultancy for reliability improvement at Digboi Refinery, of Indian Oil Corporation, INDIA Indian Oil Corporation Limited, Digboi Refinery, INDIA April, 2017 Completed None
Protection study and relay setting calculation for Tudan 132kV Substation Project of Sarawak Energy Berhad, Malaysia Alstom Services Sdn Bhd., Kuala Lumpur, Malaysia April, 2017 Completed None
Protection Study for the Waster-to-Energy Plant of National Environment Agency, Singapore GE Grid Solutions Pte Ltd, Singapore April, 2017 Completed None
Onsite consultancy for reliability improvement at Gujarat Refinery, of Indian Oil Corporation, INDIA Indian Oil Corporation Limited, Gujarat Refinery, INDIA January, 2017 Completed None
Power system study for reliability enhancement at Guwahati Refinery of Indian Oil Corporation Limited, Assam, INDIA Indian Oil Corporation Limited, Guwahati Refinery, INDIA January, 2017 Completed ETAP
Protection study for Bellara Algerian Qatari Steel Plant, Algeria ABB Germany November, 2016 Completed Digsilent
Protection System Review for 3 x 700 MW Manjung Power Plant of Tenaga Nasional Berhand, Malaysia GE Grid Solutions Pte Ltd, Singapore October, 2016 Completed None
Onsite consultancy for Retrofitting of Generator Protection System at Mangalore Refinery, Karnataka, INDIA Mangalore Refinery and Petrochemicals Limited, Karnataka, INDIA September, 2016 Completed None
Protection Setting Review for Melbourne Airport Terminal ABB Pty, Australia September, 2016 Completed None
Power System Study for 2 x 800 MW Jimah Power Plant, Malaysia Total Power Solutions, Sdn. Bad, Kuala Lumpur, Malaysia September, 2016 Completed ETAP
Onsite consultancy for reliability improvement at Haldia Refinery of Indian Oil Corporation Limited, INDIA Indian Oil Corporation Limited, Haldia Refinery, INDIA June, 2016 Completed None
Onsite consultancy for reliability improvement at Mangalore Refinery, Karnataka, INDIA Mangalore Refinery and Petrochemicals Limited, Karnataka, INDIA April, 2016 Completed None
Protection study and relay setting calculation for Tudan 275kV Substation Project of Sarawak Energy Berhad, Malaysia Alstom Services Sdn Bhd., Kuala Lumpur, Malaysia March, 2016 Completed None
Power system studies to connect the new BPSTG at HPCL Mumbai Refinery HPCL, Mumbai, INDIA February 2016 Completed ETAP
Protection relay setting calculation for 66kV Bus bar protection of Waratah Place SS, Australia ABB Pty, Australia October 2015 Completed None
Protection relay setting review for 220kV Cape Lambert Substation of RTIO, Australia ABB Pty, Australia October 2015 Completed Digsilent
Insulation co-ordination study for KVMRT Project, Kuala Lumpur, Malaysia Elenser Engineering India Private Limited July 2015 Completed ATP
On-site consultancy for protection setting review for HPCL Mumbai refinery HPCL, Mumbai, India, INDIA January 2015 Completed ETAP
On-site consultancy for power system modification to allow parallel operation with the grid at Gujarat Refinery of Indian Oil Corporation Limited IOCL Gujarat Refinery, Vadodara, INDIA January 2015 Completed None
Power system and protection study for Rabab Harweel Integrated Project of Petroleum Development of Oman Petrofac, Sharjah October 2014 Completed Digsilent
Multiple power system studies to improve the reliability of the electrical power system at the Bongaigaon refinery of Indian Oil Corporation Limited. IOCL, Bongaigaon Refinery, INDIA September, 2014 Completed ETAP
Protection study update for Blackwell substation ABB Pty, Australia October, 2014 Completed None
Protection setting review for the electrical system of Chennai Petroleum Corporation Limited at Nagapattinam, Tamil Nadu, India CPCL, Nagapattinam, Tamil Nadu, INDIA June 2014 Completed ETAP
Protection setting review for the electrical power system at the Al-Jalamid plant of Ma’aden Phosphate Company, Kingdom of Saudi Arabia Ma’aden Phosphate Company, Kingdom of Saudi Arabia May 2014 Completed ETAP
Protection setting review for he 11kV generator switchboard, of K44 Water Pump & Treatment Plant at Rumaila Oil Field, Southern Iraq Petrofac, Sharjah April 2014 Completed ETAP
Protection study for the 275kV Lachau substation of Sarawak Energy Berhad, Malaysia ALSTOM Services Bhd, Malaysia Jan 2014 Completed None
Protection study for the upgraded protection system of the Existing circuits of Hope Downs Substation of Rio Tinto, Australia ABB Pty, Australia May, 2013 Completed Digsilent
Protection study for the 220kV Cape Lambert Substation of RTIO, Australia ABB Pty, Australia May, 2013 Completed Digsilent
Power system study for the electrical system at the PVC plant of Chemaplast Sanmar at Cuddalore, India Chemaplast Sanmar Pvt. Ltd., Cuddalore, Tamil Nadu, INDIA April, 2013 Completed ETAP
Power system protection and CT adequacy study for Dugald River Mine Project of MMG Dugald River, Australia SMEC, Australia February, 2013 Completed None
Power system study for reactive power compensation analysis for Chennai Petroleum Corporation Limited, Chennai CPCL, Chennai, INDIA December, 2012 Completed ETAP
Power system protection and CT adequacy study for Nowergup Traction Project of Public Transport Authority of Western Australia ABB Pty, Australia November, 2012 Completed Digsilent
Protection study for 230kV GIS Switchyard of Sembcogen at Banyan, Singapore ALSTOM Grid, Pte., Singapore October, 2012 Completed None
Power system study for YMPS substation of Rio Tinto, Australia ABB Pty, Australia September, 2012 Completed Digsilent
Power system study for West Angelas substation of Rio Tinto, Australia ABB Pty, Australia May, 2012 Completed Digsilent
Protection system study for the 2 x 35MW power plant of Kamachi Sponge and Power Limited, Chennai, India Kamachi Sponge and Power Limited, Chennai, INDIA March, 2012 Completed ETAP
Power system study for CA33SS switchboard at Cape Lambert substation of Rio Tinto, Australia ABB Pty, Australia January, 2012 Completed Digsilent
Protection system study and relay coordination for the DHDT project of Indian Oil Corporation Bongaigaon Refinery IOCL, Bongaigaon Refinery, INDIA December, 2011 Completed ETAP
Protection study for 230kV GIS Switchyard of Keppel Merlimau Cogen II, of Keppel Merlimau Cogen Pte Ltd., Singapore ALSTOM Grid, Pte., Singapore October, 2011 Completed None
Power system study for CLSS switchboard at Cape Lambert substation of Rio Tinto, Australia ABB Pty, Australia October, 2011 Completed Digsilent
Protection study for Patikari Power house, Himachal Pradesh, India Energy Infratech Pvt. Ltd., INDIA August, 2011 Completed None
Power system study for Hope Downs and Hope Downs 4 substations of Rio Tinto, Australia ABB Pty, Australia August, 2011 Completed Digsilent
Protection system study for Borouge substation of Abu Dhabi Polymers, Abu Dhabi, ALSTOM Grid, Dubai August, 2011 Completed ETAP
Protection system study for the power system at Tom Price substation of Rio Tinto, Australia ABB Pty, Australia May, 2011 Completed Digsilent
Feasibility study for implementing circuit breaker failure protection at IOCL Digboi refinery Indian Oil Corporation Limited, Digboi Refinery, INDIA April, 2011 Completed ETAP
Protection Study and relay setting calculation for EHV transmission grid of Delhi Transmission Company Limited Central Power Research Institute, Bangalore, INDIA August, 2010 Completed None
Protection Study and relay coordination for the plant of Chemaplast Sanmar Limited, Metur Dam M N Dastur & Company, Chennai, INDIA July, 2010 Completed ETAP
Protection system study and relay coordination for Indian Oil Corporation Bongaigaon Refinery IOCL, Bongaigaon Refinery, INDIA March, 2010 Completed ETAP
Protection system study and relay coordination for Indian Oil Corporation Guwahati Refinery IOCL, Guwahati Refinery, INDIA November, 2009 Completed ETAP
Power system protection setting calculation for 132 & 11kV, JHRC and INVR substations of Dubai Electricity And Water Authority ETA, Dubai October, 2009 Completed None
Power system study for India Cements plant at, Sankarnagar, Tamil Nadu India Cements, INDIA September, 2009 Completed None
Protection system study and relay coordination for Indian Oil Corporation Digboi Refinery AREVA T&D, Chennai, INDIA April, 2009 Completed ETAP
Protection system study and relay setting calculation for traction power supply system of South Eastern Pennsylvania Transportation Authority, Philadelphia, Pennsylvania, USA AREVA T&D, France February, 2009 Completed None
Protection study for 3.3kV switchboard of Quatar Petroleum at Mesaieed Tadmur Contracting & Trading Est. November, 2008 Completed None
Power System protection relay setting and co-ordination for Chattisgarh Steel and Power Limited, Champa, India INEL Power systems (P) Ltd, INDIA November, 2008 Completed None
Protection setting calculation for Raichur Thermal Power Plant system of Karnataka Power Corporation Ltd. Central Power Research Institute, Bangalore, INDIA August, 2007 Completed None
Protection setting calculation of 220 kV grid of Delhi TRANSCO Ltd Central Power Research Institute, Bangalore, INDIA March, 2007 Completed None