S. No. | Job Description | Customer | Order Received | Status | Software |
---|---|---|---|---|---|
On-site technical consultation at Indian Oil Corporation Guwahati Refinery, Assam | Indian Oil Corporation Limited, Guwahati Refinery, INDIA | January 2025 | Completed | None | |
Power System Study for Dumad Plant of Indian Oil Corporation Limited | Indian Oil Corporation Limited, Gujarat Refinery, INDIA | December 2024 | Ongoing | ETAP | |
Power System Study for India Oil Corporation, Haldia Refinery. | SNS Technocorp Pvt. Ltd., New Delhi | September 2024 | Ongoing | ETAP | |
Consulting services for electriccal power system study at Guru Gobind Singh Refinery of HMEL, Bhatinda | HPCL-Mittal Energy Limited, Bathinda, Punjab, INDIA | July 2024 | Completed | ETAP | |
Protection Setting Study for CCP4 230kV GIS of Sembcogen at Banyan, Singapore | GE Grid Solutions Pte Ltd (GE Vernova), Singapore | June 2024 | Completed | None | |
On-site technical consultation at Indian Oil Corporation Guwahati Refinery, Assam | Indian Oil Corporation Limited, Guwahati Refinery, INDIA | April 2024 | Completed | None | |
Relay coordination study for the electrical system at Paste PVC Plant of Chemplast, Cuddalore | Chemaplast Sanmar Pvt. Ltd., Cuddalore, Tamil Nadu, INDIA | April 2024 | Completed | ETAP | |
On-site technical consultation at Indian Oil Corporation Guwahati Refinery, Assam | Indian Oil Corporation Limited, Guwahati Refinery, INDIA | October 2023 | Completed | None | |
Expert Consulting Service for developing Algorithm and Matlab code for enhancement of the Automatic Fault Analysis software (AFA2.0) and development of Web based COMTRADE reader for TNB Malaysia. | Comfort Alliance Sdn Bhd., Kuala Lumpur, Malaysia | August 2023 | Completed | Matlab, Python, Django, Javascript & React | |
Power system and protection studies for MRPL refinery and Aromatic Complex | Mangalore Refineries and Petrochemicals Limited, Mangalore, Karnataka | January 2023 | Completed | ETAP | |
Power system and protection study for CPP electrical system of Guru Gobind Singh Refinery of HMEL | HPCL-Mittal Energy Limited, Bathinda, Punjab, INDIA | December 2022 | Completed | ETAP | |
Power system and protection study for operating refinery electrical power system at IOCL Barauni refinery in parallel with 220kV grid | Indian Oil Corporation Limited, Barauni Refinery, Bihar, INDIA | December 2022 | Ongoing | ETAP | |
Expert Consulting Service for developing Algorithm and Matlab code for selected modules of the Automatic Fault Analysis software of TNB Malaysia. | Comfort Alliance Sdn Bhd., Kuala Lumpur, Malaysia | September 2022 | Completed | Matlab | |
Power system study for grid parallel operation feasibility for Indian Oil Corporation Bongaigaon Refinery | Indian Oil Corporation Limited, Bongaigaon Refinery, INDIA | June 2022 | Completed | ETAP | |
On-site technical consultation at Indian Oil Corporation Guwahati Refinery, Assam | Indian Oil Corporation Limited, Guwahati Refinery, INDIA | June 2022 | Completed | None | |
Feasibility study for new induction motor and DG addition to the LAB electrical system of Tamil Nadu Petroproducts Limited, Chennai | Tamil Nadu Petroproducts Limited, Tamil Nadu, INDIA | May 2022 | Completed | ETAP | |
Overcurrent & Earth fault setting review for BS-VI HT system at Mangalore Refineries and Petrochemicals Limited | Mangalore Refineries and Petrochemicals Limited, Mangalore, Karnataka | March 2022 | Completed | ETAP | |
Generator Protection Setting Calculation for Black Point Power Station, Hong Kong | GE Grid Solutions Pte Ltd, Singapore | March 2022 | Completed | None | |
Protection Setting Study for 400/220kV Mariakani Substation, Kenya | GE Grid Solutions Pte Ltd, Singapore | March 2022 | Completed | None | |
Power System Study for Indian Oil Coporation, Guwahati Refinery for Grid parallel operation | Siemens Ltd, Kolkatta | January 2022 | Completed | ETAP | |
Power System Study for India Oil Corporation, Panipat Refinery & Naptha Cracker Plant | SNS Technocorp Pvt. Ltd., New Delhi | January 2022 | Ongoing | ETAP | |
Algorithm development for Power Quality Module of AFA for TNB Malaysia | Comfort Alliance Sdn Bhd., Kuala Lumpur,Malaysia | January 2022 | Completed | Matlab | |
Power System Study for the plant of TCI Sanmar Chemicals, Port Said, Egypt | TCI Sanmar Chemicals S.A.E, Egypt | March 2021 | Completed | ETAP | |
Protection study for the electrical system of Tamil Nadu Pertroproducts Limited, Chennai | Tamil Nadu Petroproducts Limited, Tamil Nadu, INDIA | January 2021 | Completed | ETAP | |
Protection study for 220/132kV PAC ON substation of CEM Macau | GE Grid Solutions Limited, Hong Kong | January 2021 | Completed | None | |
Online consultancy to troubleshoot the reason for residual current observed in the generator incomers at OMPL, Mangalore and suggest solution to solve problem | ONGC Mangalore Petrochemicals Limited, Mangalore | December 2020 | Completed | None | |
Reactive Power Compensation study for power factor correction at the 6.6kV HDT and SDU S/S of IOCL Haldia Refinery | Indian Oil Corporation Limited, Digboi Refinery, INDIA | October 2020 | Completed | ETAP | |
Algorithm Development for Automatic Fault Analysis System for TNB Malaysia | Total Power Solutions, Sdn. Bad, Kuala Lumpur, Malaysia | June 2020 | Completed | Matlab | |
Protection Setting Study for REALISATION DE LA STN DE DESSALEMENT D’EAU DE MER DE ZARAT Project (De-salination plant) in Tunisia | VA TECH WABAG, India | March 2020 | Ongoing | ETAP | |
Protection setting review for the Captive Power Plant of India Cement at Sankarnagar, Tamil Nadu, INDIA | India Cement Limited | March 2020 | Completed | ETAP | |
Protection Setting Review for 33/11kV NDOOD JHAM Substation of Abu Dhabi Transmission Company | ABB, Dubai, UAE | March 2020 | Completed | None | |
Power system study for IOCL Haldia refinery | Power system study of IOCL Haldia refinery | February 2020 | Completed | ETAP | |
Protection study for the 275, 33 & 11kV TATAU substation of Sarawak Energy Berhad, Malaysia | GE Power Services (Malaysia) Sdn Bhd | February 2020 | Completed | None | |
Onsite consultancy for analysing tripping incident at IOCL Digboi Refinery | Indian Oil Corporation Limited, Digboi Refinery, INDIA | July 2019 | Completed | None | |
Protection study for Al Dhafrah 400kV Switching Station of Abu Dhabi Transmission Compay | ABB, Dubai, UAE | June 2019 | Completed | None | |
Onsite consultancy for reliability improvement at Mangalore Refineries, Karnataka | Mangalore Refinery, Karnataka, INDIA | April & Dec 2019 | Completed | None | |
Protection setting review for the LT system of India Cement at Sankarnagar, Tamil Nadu, INDIA | India Cement Limited | January, 2019 | Completed | None | |
Protection relay setting review for Haldia Refinery of Indian Oil Corporation Limited, West Bengal, INDIA | M/s Jeevandeep Enterprise | November 2018 | Completed | ETAP | |
Protection study for the 275, 132 & 33kV SERUDIT substation of Sarawak Energy Berhad, Malaysia | GE Power Services (Malaysia) Sdn Bhd | September 2018 | Completed | None | |
Onsite consultancy for reliability improvement at Mangalore Refineries, Karnataka | Mangalore Refinery, Karnataka, INDIA | April & May 2018 | Completed | None | |
Power system and protection study for Gujarat Refinery of Indian Oil Corporation Limited, Vadodara, INDIA | Siemens Ltd., INDIA | March 2018 | Completed | ETAP | |
Protection setting review for the Cement plant of India Cement at Sankarnagar, Tamil Nadu, INDIA | India Cement Limited | January, 2018 | Completed | None | |
Protection setting review for Digboi Refinery, of Indian Oil Corporation, INDIA | Indian Oil Corporation Limited, Digboi Refinery, INDIA | January, 2018 | Completed | ETAP | |
Onsite consultancy for reliability improvement at Digboi Refinery, of Indian Oil Corporation, INDIA | Indian Oil Corporation Limited, Digboi Refinery, INDIA | December, 2017 | Completed | None | |
Power system study of IOCL Bongaigaon refinery for INDMAX project | L&T, Hydrocarbon Engineering Ltd | October, 2017 | Completed | ETAP | |
Protection study for Bismayah 400/132/11kV substation, IRAQ | ABB Germany | September, 2017 | Completed | None | |
Harmonic study for analyze the effect of installing capacitor bank at Chennai Petroleum Corporation Limited, INDIA | Adarsha Control & Automation, Chennai, INDIA | May, 2017 | Completed | ETAP | |
Onsite consultancy for reliability improvement at Digboi Refinery, of Indian Oil Corporation, INDIA | Indian Oil Corporation Limited, Digboi Refinery, INDIA | April, 2017 | Completed | None | |
Protection study and relay setting calculation for Tudan 132kV Substation Project of Sarawak Energy Berhad, Malaysia | Alstom Services Sdn Bhd., Kuala Lumpur, Malaysia | April, 2017 | Completed | None | |
Protection Study for the Waster-to-Energy Plant of National Environment Agency, Singapore | GE Grid Solutions Pte Ltd, Singapore | April, 2017 | Completed | None | |
Onsite consultancy for reliability improvement at Gujarat Refinery, of Indian Oil Corporation, INDIA | Indian Oil Corporation Limited, Gujarat Refinery, INDIA | January, 2017 | Completed | None | |
Power system study for reliability enhancement at Guwahati Refinery of Indian Oil Corporation Limited, Assam, INDIA | Indian Oil Corporation Limited, Guwahati Refinery, INDIA | January, 2017 | Completed | ETAP | |
Protection study for Bellara Algerian Qatari Steel Plant, Algeria | ABB Germany | November, 2016 | Completed | Digsilent | |
Protection System Review for 3 x 700 MW Manjung Power Plant of Tenaga Nasional Berhand, Malaysia | GE Grid Solutions Pte Ltd, Singapore | October, 2016 | Completed | None | |
Onsite consultancy for Retrofitting of Generator Protection System at Mangalore Refinery, Karnataka, INDIA | Mangalore Refinery and Petrochemicals Limited, Karnataka, INDIA | September, 2016 | Completed | None | |
Protection Setting Review for Melbourne Airport Terminal | ABB Pty, Australia | September, 2016 | Completed | None | |
Power System Study for 2 x 800 MW Jimah Power Plant, Malaysia | Total Power Solutions, Sdn. Bad, Kuala Lumpur, Malaysia | September, 2016 | Completed | ETAP | |
Onsite consultancy for reliability improvement at Haldia Refinery of Indian Oil Corporation Limited, INDIA | Indian Oil Corporation Limited, Haldia Refinery, INDIA | June, 2016 | Completed | None | |
Onsite consultancy for reliability improvement at Mangalore Refinery, Karnataka, INDIA | Mangalore Refinery and Petrochemicals Limited, Karnataka, INDIA | April, 2016 | Completed | None | |
Protection study and relay setting calculation for Tudan 275kV Substation Project of Sarawak Energy Berhad, Malaysia | Alstom Services Sdn Bhd., Kuala Lumpur, Malaysia | March, 2016 | Completed | None | |
Power system studies to connect the new BPSTG at HPCL Mumbai Refinery | HPCL, Mumbai, INDIA | February 2016 | Completed | ETAP | |
Protection relay setting calculation for 66kV Bus bar protection of Waratah Place SS, Australia | ABB Pty, Australia | October 2015 | Completed | None | |
Protection relay setting review for 220kV Cape Lambert Substation of RTIO, Australia | ABB Pty, Australia | October 2015 | Completed | Digsilent | |
Insulation co-ordination study for KVMRT Project, Kuala Lumpur, Malaysia | Elenser Engineering India Private Limited | July 2015 | Completed | ATP | |
On-site consultancy for protection setting review for HPCL Mumbai refinery | HPCL, Mumbai, India, INDIA | January 2015 | Completed | ETAP | |
On-site consultancy for power system modification to allow parallel operation with the grid at Gujarat Refinery of Indian Oil Corporation Limited | IOCL Gujarat Refinery, Vadodara, INDIA | January 2015 | Completed | None | |
Power system and protection study for Rabab Harweel Integrated Project of Petroleum Development of Oman | Petrofac, Sharjah | October 2014 | Completed | Digsilent | |
Multiple power system studies to improve the reliability of the electrical power system at the Bongaigaon refinery of Indian Oil Corporation Limited. | IOCL, Bongaigaon Refinery, INDIA | September, 2014 | Completed | ETAP | |
Protection study update for Blackwell substation | ABB Pty, Australia | October, 2014 | Completed | None | |
Protection setting review for the electrical system of Chennai Petroleum Corporation Limited at Nagapattinam, Tamil Nadu, India | CPCL, Nagapattinam, Tamil Nadu, INDIA | June 2014 | Completed | ETAP | |
Protection setting review for the electrical power system at the Al-Jalamid plant of Ma’aden Phosphate Company, Kingdom of Saudi Arabia | Ma’aden Phosphate Company, Kingdom of Saudi Arabia | May 2014 | Completed | ETAP | |
Protection setting review for he 11kV generator switchboard, of K44 Water Pump & Treatment Plant at Rumaila Oil Field, Southern Iraq | Petrofac, Sharjah | April 2014 | Completed | ETAP | |
Protection study for the 275kV Lachau substation of Sarawak Energy Berhad, Malaysia | ALSTOM Services Bhd, Malaysia | Jan 2014 | Completed | None | |
Protection study for the upgraded protection system of the Existing circuits of Hope Downs Substation of Rio Tinto, Australia | ABB Pty, Australia | May, 2013 | Completed | Digsilent | |
Protection study for the 220kV Cape Lambert Substation of RTIO, Australia | ABB Pty, Australia | May, 2013 | Completed | Digsilent | |
Power system study for the electrical system at the PVC plant of Chemaplast Sanmar at Cuddalore, India | Chemaplast Sanmar Pvt. Ltd., Cuddalore, Tamil Nadu, INDIA | April, 2013 | Completed | ETAP | |
Power system protection and CT adequacy study for Dugald River Mine Project of MMG Dugald River, Australia | SMEC, Australia | February, 2013 | Completed | None | |
Power system study for reactive power compensation analysis for Chennai Petroleum Corporation Limited, Chennai | CPCL, Chennai, INDIA | December, 2012 | Completed | ETAP | |
Power system protection and CT adequacy study for Nowergup Traction Project of Public Transport Authority of Western Australia | ABB Pty, Australia | November, 2012 | Completed | Digsilent | |
Protection study for 230kV GIS Switchyard of Sembcogen at Banyan, Singapore | ALSTOM Grid, Pte., Singapore | October, 2012 | Completed | None | |
Power system study for YMPS substation of Rio Tinto, Australia | ABB Pty, Australia | September, 2012 | Completed | Digsilent | |
Power system study for West Angelas substation of Rio Tinto, Australia | ABB Pty, Australia | May, 2012 | Completed | Digsilent | |
Protection system study for the 2 x 35MW power plant of Kamachi Sponge and Power Limited, Chennai, India | Kamachi Sponge and Power Limited, Chennai, INDIA | March, 2012 | Completed | ETAP | |
Power system study for CA33SS switchboard at Cape Lambert substation of Rio Tinto, Australia | ABB Pty, Australia | January, 2012 | Completed | Digsilent | |
Protection system study and relay coordination for the DHDT project of Indian Oil Corporation Bongaigaon Refinery | IOCL, Bongaigaon Refinery, INDIA | December, 2011 | Completed | ETAP | |
Protection study for 230kV GIS Switchyard of Keppel Merlimau Cogen II, of Keppel Merlimau Cogen Pte Ltd., Singapore | ALSTOM Grid, Pte., Singapore | October, 2011 | Completed | None | |
Power system study for CLSS switchboard at Cape Lambert substation of Rio Tinto, Australia | ABB Pty, Australia | October, 2011 | Completed | Digsilent | |
Protection study for Patikari Power house, Himachal Pradesh, India | Energy Infratech Pvt. Ltd., INDIA | August, 2011 | Completed | None | |
Power system study for Hope Downs and Hope Downs 4 substations of Rio Tinto, Australia | ABB Pty, Australia | August, 2011 | Completed | Digsilent | |
Protection system study for Borouge substation of Abu Dhabi Polymers, Abu Dhabi, | ALSTOM Grid, Dubai | August, 2011 | Completed | ETAP | |
Protection system study for the power system at Tom Price substation of Rio Tinto, Australia | ABB Pty, Australia | May, 2011 | Completed | Digsilent | |
Feasibility study for implementing circuit breaker failure protection at IOCL Digboi refinery | Indian Oil Corporation Limited, Digboi Refinery, INDIA | April, 2011 | Completed | ETAP | |
Protection Study and relay setting calculation for EHV transmission grid of Delhi Transmission Company Limited | Central Power Research Institute, Bangalore, INDIA | August, 2010 | Completed | None | |
Protection Study and relay coordination for the plant of Chemaplast Sanmar Limited, Metur Dam | M N Dastur & Company, Chennai, INDIA | July, 2010 | Completed | ETAP | |
Protection system study and relay coordination for Indian Oil Corporation Bongaigaon Refinery | IOCL, Bongaigaon Refinery, INDIA | March, 2010 | Completed | ETAP | |
Protection system study and relay coordination for Indian Oil Corporation Guwahati Refinery | IOCL, Guwahati Refinery, INDIA | November, 2009 | Completed | ETAP | |
Power system protection setting calculation for 132 & 11kV, JHRC and INVR substations of Dubai Electricity And Water Authority | ETA, Dubai | October, 2009 | Completed | None | |
Power system study for India Cements plant at, Sankarnagar, Tamil Nadu | India Cements, INDIA | September, 2009 | Completed | None | |
Protection system study and relay coordination for Indian Oil Corporation Digboi Refinery | AREVA T&D, Chennai, INDIA | April, 2009 | Completed | ETAP | |
Protection system study and relay setting calculation for traction power supply system of South Eastern Pennsylvania Transportation Authority, Philadelphia, Pennsylvania, USA | AREVA T&D, France | February, 2009 | Completed | None | |
Protection study for 3.3kV switchboard of Quatar Petroleum at Mesaieed | Tadmur Contracting & Trading Est. | November, 2008 | Completed | None | |
Power System protection relay setting and co-ordination for Chattisgarh Steel and Power Limited, Champa, India | INEL Power systems (P) Ltd, INDIA | November, 2008 | Completed | None | |
Protection setting calculation for Raichur Thermal Power Plant system of Karnataka Power Corporation Ltd. | Central Power Research Institute, Bangalore, INDIA | August, 2007 | Completed | None | |
Protection setting calculation of 220 kV grid of Delhi TRANSCO Ltd | Central Power Research Institute, Bangalore, INDIA | March, 2007 | Completed | None |